A construction change order review starts with a plain sentence about the work. Write what changed, which drawing or written request describes it, and when the crew needs a decision. The change order review card keeps that decision next to its budget and schedule effects.
Capture the version and the scope
Open a row or card for one change. Identify the drawing sheet, issue date or field condition and the room, zone or work package it affects. Write the original scope and the requested scope in two short lines. Use the description that the estimator, superintendent and owner can all recognize.
If a sketch or new revision is circulating, give the person who maintains the job records one copy to file. Use the same change reference when an updated drawing, quote or approval comes in.
Separate priced items from open items
Put firm vendor quotes, estimates and unknown items in their own places. Note the date and scope each quote covers. If a new detail removes part of an existing package, flag the possible credit separately for review. Ask whether delivery, engineering, permit changes, rework or another affected trade belongs in the review. Some of those costs may remain open while the immediate field decision has a deadline.
Use the builder worksheet to record an upcoming milestone affected by the change. If the change also moves a supplier’s due date, follow the vendor due-date guide to track the two dates separately.
Follow one hypothetical change
An owner requests a wider glazed opening on a spec home. The superintendent identifies the drawing revision, notes the affected wall and finds the date when the frame crew needs direction. The estimator collects the new glazing quote and records engineering as a separate open item. The job lead asks whether the new opening changes the delivery slot or the order of inspections. The owner receives one version of the proposed change with the priced items, open items and date for a decision.
The field card shows the decision needed now and who can approve it under the project’s written process. Keep the contract, lender guidance and approved documents with the parties handling those records.
Record approval and tell the affected team
Capture the decision, date, approved scope and approval reference. If part of a change stays open, give it an owner and a check-in date. Tell the crew which work can proceed using the approved instructions. Then update the job schedule and budget with the same change reference so the team can find it at the next draw or milestone review.
Take the card and the affected dates when you prepare a construction project inquiry.
Questions people ask
Who decides whether the crew can proceed?
Follow the project’s written approval process and have the authorized person record the scope, date and approval reference before the affected team acts.
Should I add an unpriced component to the approved amount?
List it as an open item with its scope, owner and next check-in. The authorized parties can decide how to handle that item using the project’s process.